Project Scope And Execution
SNCR system upgrade at a California cement plant. By constructing the new containment system around the existing operating tank, Turnell minimized plant downtime and completed the final system switchover in just 16 hours. The project included a new 20,000-gallon storage tank, truck unloading, pump and control skids, more than 1,000 feet of piping, and a new concrete containment area.